In reference to Impact Assessment of CSR Activities, answer the following: Whether the impact assessment needs to be done for an ongoing project in respect of which an outlay of ₹1 crore or more has been made in the fina

CS Professional · CSR and Social Governance · PYQS · June 2024
In reference to Impact Assessment of CSR Activities, answer the following: Whether the impact assessment needs to be done for an ongoing project in respect of which an outlay of ₹1 crore or more has been made in the financial year but the project is not yet completed?

Answer & Explanation:

Impact assessment is required to be done only after project is completed. If the project is on going or not yet completed, even if the outlay has exceeded ₹1 crore, impact assessment is not mandatory in that financial year. The Impact Assessment should be conducted for those projects, which have completed one year or for on-going projects (period more than three years).

Topics: Corporate Social Responsibility (CSR)

Open in Interactive Practice Hub · Full Practice Hub · Chapter Weightage · More in this subject

Related Questions in this Topic