Future Construction Ltd. was awarded with a contract worth ₹10,00,000. Following expenses were incurred by the company for the year ended 31 st March, 2012: ₹ Plant issued to contract 1,00,000 Material 2,00,000 Wages 2,5
CS Executive · Cost and Management Accounting · PYQS · December 2013
Future Construction Ltd. was awarded with a contract worth ₹10,00,000. Following expenses were incurred by the company for the year ended 31 st March, 2012: ₹ Plant issued to contract 1,00,000 Material 2,00,000 Wages 2,50,000 Hire charges 50,000 Electricity 1,00,000 Administration overheads 60,000 Of the plant issued to the contract, a part with the original cost of ₹40,000 was sold for ₹50,000 on 1 st April, 2011. Plant is subject to depreciation @10% per annum. Material worth ₹20,000 were in stock as on 31 st March, 2012. As on 31 st March, 2012, the company received ₹7,20,000 by way of cash being 80% of the work certified. Cost of uncertified work as on 31 st March, 2012 was ₹30,000. The company is expecting to complete the contract by 30 th June, 2012, for which the following additional expenditure are expected to be incurred: ₹ Material (in addition to material in hand) 40,000 Wages 30,000 Administration overheads 5,000 Contingency : 5% of total cost excluding contingency. You are required to prepare contract account for the year ended 31 st March, 2012.
Topics: Contract Costing
Related Questions in this Topic
- 92. A contract is completed to the extent of two-third. It shows a loss of ₹1,20,000 at the end of the accounting period...
- 76. In contract costing, which of the following clauses provides safeguard against any fluctuation in the prices of mate...
- 28. XYZ contractor provides the following information: Contract price is ₹4,00,000. Cash received on account was ₹3,00,0...
- The cost of sub-contracts is :
- Value of work certified + Cost of work uncertified - Reserve for unrealised profit - Amount received from the contractee...