28. XYZ contractor provides the following information: Contract price is ₹4,00,000. Cash received on account was ₹3,00,000. Work certified ₹3,50,000. Cost of work done up to date ₹2,95,000. Calculate profit to be conside

CS Executive · Cost and Management Accounting · PYQS · June 2021
28. XYZ contractor provides the following information: Contract price is ₹4,00,000. Cash received on account was ₹3,00,000. Work certified ₹3,50,000. Cost of work done up to date ₹2,95,000. Calculate profit to be considered on contract.
(A) ₹15714.43
(B) ₹42777.27
(C) ₹31428.57
(D) ₹21389.63

Answer & Explanation:

Correct Answer: Option (C)

Official answer key: (C).

Topics: Contract Costing