From the following information, compute (i) Material cost variance; (ii) Material price variance; and (iii) Material usage variance. Quantity of material purchased: 3,000 units Value of materials purchased: ₹9,000 Standa

CS Executive · Cost and Management Accounting · PYQS · June 2014
From the following information, compute (i) Material cost variance; (ii) Material price variance; and (iii) Material usage variance. Quantity of material purchased: 3,000 units Value of materials purchased: ₹9,000 Standard quantity of material required per ton of output: 30 units Standard rate of material per unit: ₹2.50 Opening stock of material: Nil Closing stock of material: 500 units Output during the period: 80 tons

Topics: Standard Costing