51. Examine the following relating to Job No. 100: Standard hours planned 104.50 Actual hours worked 101.25 Standard wage rate ₹5.15 Actual wage rate ₹5.25 The total labour cost variance for Job No. 100 is ..........

CS Executive · Cost and Management Accounting · PYQS · June 2021
51. Examine the following relating to Job No. 100: Standard hours planned 104.50 Actual hours worked 101.25 Standard wage rate ₹5.15 Actual wage rate ₹5.25 The total labour cost variance for Job No. 100 is ..........
(A) ₹6.61 (F)
(B) ₹6.61 (A)
(C) ₹10.12 (F)
(D) ₹10.12 (A)

Answer & Explanation:

Correct Answer: Option (A)

Official answer key: (A).

Topics: Standard Costing