The following data is obtained from the books of a company: Normal overheads rate: ₹3.00 Actual hours operated: 20,000 Allowed hours for actual production: 21,000 Allowed overheads for budgeted hours: 70,000 Actual overh
CS Executive · Cost and Management Accounting · PYQS · June 2014
The following data is obtained from the books of a company: Normal overheads rate: ₹3.00 Actual hours operated: 20,000 Allowed hours for actual production: 21,000 Allowed overheads for budgeted hours: 70,000 Actual overheads: 72,000 Calculate: Overheads budget variance Overheads volume variance Overheads efficiency variance and Overheads capacity variance.
Topics: Standard Costing
Related Questions in this Topic
- 90. Statement I : Standard cost is a pre-determined cost. Statement II : All pre-determined costs are standard in nature...
- 89. Overhead cost variance is ₹9,000 (A), overhead expenditure variance is ₹2,000 (A) and overhead efficiency variance i...
- 81. The following are relating to Job No. 102: Standard hours planned 40.0 Actual hours worked 36.5 Standard wage rate ₹...
- 52. Which of the following is not a reason for an idle time variance ?
- 51. Examine the following relating to Job No. 100: Standard hours planned 104.50 Actual hours worked 101.25 Standard wag...