From the following data, calculate variable overheads expenditure variance: Budgeted production : 300 units Budgeted variable overheads : ₹7,800 Standard time for one unit : 20 hours Actual production : 250 units Actual

CS Executive · Cost and Management Accounting · PYQS · December 2014
From the following data, calculate variable overheads expenditure variance: Budgeted production : 300 units Budgeted variable overheads : ₹7,800 Standard time for one unit : 20 hours Actual production : 250 units Actual hours worked : 4,500 hours Actual variable overheads : ₹7,000
(A) ₹1,150 (F)
(B) ₹1,150 (A)
(C) ₹500 (A)
(D) ₹500 (F).

Answer & Explanation:

Correct Answer: Option (B)

Correct answer: (B) ₹1,150 (A). Standard variable-overhead rate/hour = 7,800/(300×20) = 1.30; expenditure variance = 4,500×1.30−7,000 = 1,150 adverse.

Topics: Standard Costing