Find the labour efficiency variance from the following information : Actual hours worked : 5,600 Actual wages paid : ₹7,840 Standard rate @ ₹2 per hour Standard hours produced : 4,000

CS Executive · Cost and Management Accounting · PYQS · December 2014
Find the labour efficiency variance from the following information : Actual hours worked : 5,600 Actual wages paid : ₹7,840 Standard rate @ ₹2 per hour Standard hours produced : 4,000
(A) ₹3,200 (A)
(B) ₹3,200 (F)
(C) ₹3,360 (F)
(D) ₹3,360 (A).

Answer & Explanation:

Correct Answer: Option (A)

Correct answer: (A) ₹3,200 (A). Labour efficiency variance = (4,000−5,600)×2 = 3,200 adverse.

Topics: Standard Costing