In contract costing, if the amount of work certified is 1/4 th or more but less than 1/2 of the 'contract price', profit to be transferred to the profit and loss account can be calculated as —
CS Executive · Cost and Management Accounting · PYQS · December 2014
In contract costing, if the amount of work certified is 1/4 th or more but less than 1/2 of the 'contract price', profit to be transferred to the profit and loss account can be calculated as —
Answer & Explanation:
Correct Answer: Option (A)
Correct answer: (A) 1/3 x Notional profit x {Cash received / Work certified}.
Topics: Contract Costing
Related Questions in this Topic
- 92. A contract is completed to the extent of two-third. It shows a loss of ₹1,20,000 at the end of the accounting period...
- 76. In contract costing, which of the following clauses provides safeguard against any fluctuation in the prices of mate...
- 28. XYZ contractor provides the following information: Contract price is ₹4,00,000. Cash received on account was ₹3,00,0...
- The cost of sub-contracts is :
- Value of work certified + Cost of work uncertified - Reserve for unrealised profit - Amount received from the contractee...