The terms of contract provide that whole of the amount shown by the architect's certificate shall not be paid immediately but a percentage thereof shall be paid. The amount not paid is termed as —

CS Executive · Cost and Management Accounting · PYQS · December 2014
The terms of contract provide that whole of the amount shown by the architect's certificate shall not be paid immediately but a percentage thereof shall be paid. The amount not paid is termed as —
(A) Lost money
(B) Retention money
(C) Advance money
(D) Contract amount.

Answer & Explanation:

Correct Answer: Option (B)

Correct answer: (B) Retention money.

Topics: Contract Costing