The standard hourly rate is ₹5 per hour and actual rate ₹4.50 per hour. If the labour rate variance is ₹1,500(F), the actual labour hours worked is —

CS Executive · Cost and Management Accounting · PYQS · June 2015
The standard hourly rate is ₹5 per hour and actual rate ₹4.50 per hour. If the labour rate variance is ₹1,500(F), the actual labour hours worked is —
(A) 1,500 hours
(B) 7,500 hours
(C) 3,000 hours
(D) 6,750 hours.

Answer & Explanation:

Correct Answer: Option (C)

Official answer key: (C).

Topics: Standard Costing