Standard hourly rate is ₹5 per hour and actual rate ₹4.50 per hour. The labour rate variance is ₹1,500(F). The actual labour hours worked is —

CS Executive · Cost and Management Accounting · PYQS · June 2015
Standard hourly rate is ₹5 per hour and actual rate ₹4.50 per hour. The labour rate variance is ₹1,500(F). The actual labour hours worked is —
(A) 1,500 Hours
(B) 7,500 Hours
(C) 3,000 Hours
(D) 6,750 Hours.

Answer & Explanation:

Correct Answer: Option (C)

Official answer key: (C).

Topics: Standard Costing

Open in Interactive Practice Hub · Full Practice Hub · Chapter Weightage · More in this subject

Related Questions in this Topic