The following data relates to two activity levels of production: Level I Level II No. of units 4,000 5,500 Overheads (₹) 2,80,000 3,50,000 Variable cost per unit would be —

CS Executive · Cost and Management Accounting · PYQS · June 2015
The following data relates to two activity levels of production: Level I Level II No. of units 4,000 5,500 Overheads (₹) 2,80,000 3,50,000 Variable cost per unit would be —
(A) ₹46.67
(B) ₹133.33
(C) ₹70
(D) ₹64.

Answer & Explanation:

Correct Answer: Option (A)

Official answer key: (A).

Topics: Overhead Costing