The following information relates to a production department of Cheenu Limited : ₹ Material used 5,00,000 Direct labour 4,00,000 Factory overhead 2,25,000 In an order carried out in the department, direct material amount

CS Executive · Cost and Management Accounting · PYQS · December 2018
The following information relates to a production department of Cheenu Limited : ₹ Material used 5,00,000 Direct labour 4,00,000 Factory overhead 2,25,000 In an order carried out in the department, direct material amounted to ₹60,000 and direct labour amounted to ₹35,000. On the basis of prime cost, amount of the factory overhead chargeable to this order will be :
(A) ₹19,688
(B) ₹23,750
(C) ₹27,000
(D) ₹42,750

Answer & Explanation:

Correct Answer: Option (B)

Official answer key: (B).

Topics: Overhead Costing