Standard rate of wages ₹0.90 per hour; standard output 20 units per hour; actual wages paid ₹76 for 80 hours (idle time 10 hours). Output produced 1,640 units. Direct labour rate variance is —

CS Executive · Cost and Management Accounting · PYQS · December 2015
Standard rate of wages ₹0.90 per hour; standard output 20 units per hour; actual wages paid ₹76 for 80 hours (idle time 10 hours). Output produced 1,640 units. Direct labour rate variance is —
(A) ₹4.00 (A)
(B) ₹4.00 (F)
(C) ₹4.20 (F)
(D) ₹4.20 (A).

Answer & Explanation:

Correct Answer: Option (A)

Official answer key: (A).