In contract costing, the whole of the amount shown under architect's certificate is not paid immediately, but a part thereof is paid after the contract is completed. Such amount is known as —

CS Executive · Cost and Management Accounting · PYQS · December 2015
In contract costing, the whole of the amount shown under architect's certificate is not paid immediately, but a part thereof is paid after the contract is completed. Such amount is known as —
(A) Retention money
(B) Advance money
(C) Contract amount
(D) Work-in-progress.

Answer & Explanation:

Correct Answer: Option (A)

Official answer key: (A).

Topics: Contract Costing