Match the following: List-I List-II P. Labour cost variance 1. Actual hours paid × (Standard rate - Actual rate) Q. Labour rate variance 2. Standard cost - Actual cost R. Efficiency variance 3. Idle hours × Standard rate

CS Executive · Cost and Management Accounting · PYQS · December 2015
Match the following: List-I List-II P. Labour cost variance 1. Actual hours paid × (Standard rate - Actual rate) Q. Labour rate variance 2. Standard cost - Actual cost R. Efficiency variance 3. Idle hours × Standard rate per hour S. Idle time variance 4. Standard rate × (Standard hours - Actual hours worked) Select the correct answer from the options given below — P Q R S
(A) 4 3 2 1
(B) 2 3 4 1
(C) 4 1 2 3
(D) 2 1 4 3

Answer & Explanation:

Correct Answer: Option (D)

Official answer key: (D).

Topics: Standard Costing