Match the following: List-I List-II P. Material cost variance 1. SP (RSQ-AQ) Q. Material price variance 2. SP (SQ-AQ) R. Material usage variance 3. AQ (SP-AP) S. Material mix variance 4. SC-AC Select the correct answer f

CS Executive · Cost and Management Accounting · PYQS · December 2015
Match the following: List-I List-II P. Material cost variance 1. SP (RSQ-AQ) Q. Material price variance 2. SP (SQ-AQ) R. Material usage variance 3. AQ (SP-AP) S. Material mix variance 4. SC-AC Select the correct answer from the options given below — P Q R S
(A) 4 3 2 1
(B) 2 1 4 3
(C) 4 1 2 3
(D) 3 4 2 1

Answer & Explanation:

Correct Answer: Option (A)

Official answer key: (A).

Topics: Standard Costing