Following information is supplied regarding a contract in progress : Details Amount (₹) Stage of completion (%) Erection cost to date 7,500 25 Fabrication cost to date: Material 60,000 60 Wages and other expenses 47,500

CS Executive · Cost and Management Accounting · PYQS · June 2016
Following information is supplied regarding a contract in progress : Details Amount (₹) Stage of completion (%) Erection cost to date 7,500 25 Fabrication cost to date: Material 60,000 60 Wages and other expenses 47,500 50 Contract value 2,00,000 The estimated profit or loss at the completion of the contract will be —
(A) ₹25,000 (Profit)
(B) ₹25,000 (Loss)
(C) ₹26,000 (Profit)
(D) ₹26,000 (Loss).

Answer & Explanation:

Correct Answer: Option (B)

Official answer key: (B).

Topics: Contract Costing