Following information is given : Standard fixed overheads rate per hour: ₹5 Budgeted hours: 12,500 Standard number of working days: 25 Actual hours: 11,500 Actual number of working days: 22 Calendar variance will be —
CS Executive · Cost and Management Accounting · PYQS · June 2016
Following information is given : Standard fixed overheads rate per hour: ₹5 Budgeted hours: 12,500 Standard number of working days: 25 Actual hours: 11,500 Actual number of working days: 22 Calendar variance will be —
Answer & Explanation:
Correct Answer: Option (D)
Official answer key: (D).
Topics: Overhead Costing