Which of the following statements is wrong with reference to contract costing —

CS Executive · Cost and Management Accounting · PYQS · June 2016
Which of the following statements is wrong with reference to contract costing —
(A) Cost plus contract is suitable where it is not possible to compute the cost in advance
(B) Upward and downward revision may be possible in contract price by inserting escalation/de-escalation clause
(C) If certified work-in-progress is ¼ or more but less than ½ of the contract price, no profit is to be transferred to profit and loss account
(D) Loss on incomplete contracts should be transferred to profit and loss account.

Answer & Explanation:

Correct Answer: Option (C)

Official answer key: (C).

Topics: Contract Costing