The difference between actual price and standard price multiplied by actual quantity will result into:

CS Executive · Cost and Management Accounting · PYQS · June 2017
The difference between actual price and standard price multiplied by actual quantity will result into:
(A) Material quantity variance
(B) Material mix variance
(C) Material price variance
(D) Material yield variance

Answer & Explanation:

Correct Answer: Option (C)

Official answer key: (C).

Topics: Standard Costing