Material cost variance is due to :

CS Executive · Cost and Management Accounting · PYQS · June 2017
Material cost variance is due to :
(A) Change in price of material
(B) Change in quantity used
(C) Change in material mix
(D) All of the above

Answer & Explanation:

Correct Answer: Option (D)

Official answer key: (D).

Topics: Standard Costing