In an analysis of labour cost variance it was ascertained that the labour rate variance was ₹750 A, actual time was 1,500 hours and standard rate per hour is ₹1.50. The actual rate per hour was: (A) ₹1.00 (B) ₹2.00 (C) ₹

CS Executive · Cost and Management Accounting · PYQS · December 2017
In an analysis of labour cost variance it was ascertained that the labour rate variance was ₹750 A, actual time was 1,500 hours and standard rate per hour is ₹1.50. The actual rate per hour was: (A) ₹1.00 (B) ₹2.00 (C) ₹2.5 (D) None of the above
(A) ₹1.00
(B) ₹2.00
(C) ₹2.5
(D) None of the above

Answer & Explanation:

Correct Answer: Option (B)

Official answer key: (B).

Topics: Standard Costing