The following are the information taken from the cost records of a contract which was 90% completed : ₹ Total expenditure to date 20,50,000 Contract Price 32,00,000 Work certified 27,00,000 Work uncertified 1,80,000 Cash received 22,50,000 Estimated future expenditure to complete the contract 1,50,000 The estimated profit is: (A) ₹2,00,000 (B) ₹10,00,000 (C) ₹11,50,000 (D) ₹50,000
(A) ₹2,00,000
(B) ₹10,00,000
(C) ₹11,50,000
(D) ₹50,000

Answer & Explanation:

Correct Answer: Option (B)

Official answer key: (B).