The standard referred to the target which can be attained under the most favourable conditions with no allowance for normal losses, waste and machine down time, is known as:
CS Executive · Cost and Management Accounting · PYQS · December 2018
The standard referred to the target which can be attained under the most favourable conditions with no allowance for normal losses, waste and machine down time, is known as:
Answer & Explanation:
Correct Answer: Option (D)
Official answer key: (D).
Topics: Standard Costing
Related Questions in this Topic
- 90. Statement I : Standard cost is a pre-determined cost. Statement II : All pre-determined costs are standard in nature...
- 89. Overhead cost variance is ₹9,000 (A), overhead expenditure variance is ₹2,000 (A) and overhead efficiency variance i...
- 81. The following are relating to Job No. 102: Standard hours planned 40.0 Actual hours worked 36.5 Standard wage rate ₹...
- 52. Which of the following is not a reason for an idle time variance ?
- 51. Examine the following relating to Job No. 100: Standard hours planned 104.50 Actual hours worked 101.25 Standard wag...