Direct labour cost data are as follows: Actual hours worked 25,000, Total direct labour cost ₹1,25,400, Direct labour rate variance ₹2,900 (A), Direct labour efficiency variance ₹3,528 (F) Standard labour hour rate will

CS Executive · Cost and Management Accounting · PYQS · June 2019
Direct labour cost data are as follows: Actual hours worked 25,000, Total direct labour cost ₹1,25,400, Direct labour rate variance ₹2,900 (A), Direct labour efficiency variance ₹3,528 (F) Standard labour hour rate will be ________.
(A) ₹5.02
(B) ₹5.26
(C) ₹4.90
(D) ₹5.16

Answer & Explanation:

Correct Answer: Option (C)

Official answer key: (C).

Topics: Standard Costing