Examine the following relating to Job No. 999: Standard hours planned | 28.0 Actual hours worked | 26.5 Standard wage rate | ₹5.60 Actual wage rate | ₹6.05 Assume that there is no idle time The labour efficiency variance

CS Executive · Cost and Management Accounting · PYQS · December 2019
Examine the following relating to Job No. 999: Standard hours planned | 28.0 Actual hours worked | 26.5 Standard wage rate | ₹5.60 Actual wage rate | ₹6.05 Assume that there is no idle time The labour efficiency variance for Job No. 999 is ............
(A) ₹9.08 (F)
(B) ₹8.40 (F)
(C) ₹11.93 (A)
(D) ₹3.53 (A)

Answer & Explanation:

Correct Answer: Option (B)

Official answer key: (B).

Topics: Standard Costing