Following data are given : (i) Gross Direct Wages ₹15,000 (ii) Standard hours produced = 7600 (iii) Standard Rate per hour = ₹2.10 (iv) Actual hours paid @ ₹2.40 are 7500, out of which hours not worked (abnormal idle tim

CS Executive · Cost and Management Accounting · PYQS · December 2020
Following data are given : (i) Gross Direct Wages ₹15,000 (ii) Standard hours produced = 7600 (iii) Standard Rate per hour = ₹2.10 (iv) Actual hours paid @ ₹2.40 are 7500, out of which hours not worked (abnormal idle time) are 75 hours. Labour efficiency variance is :
(A) ₹240 (A)
(B) ₹210 (F)
(C) ₹367.50 (F)
(D) ₹420 (F)

Answer & Explanation:

Correct Answer: Option (C)

Official answer key: (C).

Topics: Standard Costing