You are given the following information : Contract Price ₹75,00,000 Cumulative figures: (i) To end of previous period — profit recognized ₹12,25,000 (ii) To end of current period — total costs ₹41,50,000 (iii) Cost of wo

CS Executive · Cost and Management Accounting · PYQS · December 2020
You are given the following information : Contract Price ₹75,00,000 Cumulative figures: (i) To end of previous period — profit recognized ₹12,25,000 (ii) To end of current period — total costs ₹41,50,000 (iii) Cost of work certified ₹54,00,000 (iv) Estimated future costs to completion ₹7,25,000 (v) Estimated rectification costs 15% of contract price The profit/loss to be recognized as per AS 7 in the current period is :
(A) Profit ₹21,00,000
(B) Profit ₹3,00,000
(C) Profit ₹1,25,000
(D) Loss ₹2,75,000

Answer & Explanation:

Correct Answer: Option (C)

Official answer key: (C).

Topics: Contract Costing