18. The following data were taken from the cost records for the week ended on 31st March, 2021: Budgeted fixed overhead ₹1400 Standard output for 40 hours per week 1400 units Actual output 1200 units Actual hours worked

CS Executive · Cost and Management Accounting · PYQS · June 2021
18. The following data were taken from the cost records for the week ended on 31st March, 2021: Budgeted fixed overhead ₹1400 Standard output for 40 hours per week 1400 units Actual output 1200 units Actual hours worked 32 If the actual fixed overhead was ₹1500, the capacity variance is:
(A) ₹299.6 A
(B) ₹280 A
(C) ₹80 F
(D) ₹85.6 F

Answer & Explanation:

Correct Answer: Option (B)

Official answer key: (B).

Topics: Standard Costing

Open in Interactive Practice Hub · Full Practice Hub · Chapter Weightage · More in this subject

Related Questions in this Topic