CPM computes the path of planned jobs/activities to logical end points/the end of the project, and the earliest and latest time by which each activity can start and finish without making the project longer. This process

CS Executive · Financial and Strategic Management · PYQS · June 2023
CPM computes the path of planned jobs/activities to logical end points/the end of the project, and the earliest and latest time by which each activity can start and finish without making the project longer. This process determines the activities that are "__________" or on the longest path and having "total float".
(A) Shortest; Crucial
(B) Shortest; Critical
(C) Longest; Critical
(D) Longest; Feasible

Answer & Explanation:

Correct Answer: Option (C)

Official answer key: (C).