In projects like Civil Construction and Ship building, which of the following is more suitable ?

CS Executive · Financial and Strategic Management · PYQS · December 2023
In projects like Civil Construction and Ship building, which of the following is more suitable ?
(A) PERT
(B) CPM
(C) Both
(D) Neither CPM nor PERT

Answer & Explanation:

Correct Answer: Option (B)

Official answer key: (B).