Compare PERT and CPM-based on its : Meaning, Orientation, Model, Focus, Suitability.

CS Professional · Strategic Management and Corporate Finance · PYQS · December 2025
Compare PERT and CPM-based on its : Meaning, Orientation, Model, Focus, Suitability.

Answer & Explanation:

Basis for Comparison PERT CPM Meaning PERT is a project management technique, used to manage uncertain activities of a project CPM is a statistical technique of project management that manages well defined activities of a project Orientation Event-oriented Activity-oriented Model Probabilistic Model Deterministic Model Focus Time Time-cost trade-off Suitability Research and Development Project Non-research projects like civil construction, ship building etc.