Rim Industries Limited (Referred as 'Rim Limited'), a supplier of industrial equipment entered into a contract with Sanju Products Private Limited (Referred as 'SPPL'), for supply and installation of machinery. The agree
CS Professional · Arbitration, Mediation and Conciliation · PYQS · June 2026
Rim Industries Limited (Referred as 'Rim Limited'), a supplier of industrial equipment entered into a contract with Sanju Products Private Limited (Referred as 'SPPL'), for supply and installation of machinery. The agreement contained an arbitration clause providing that dispute would be resolved through arbitration by a sole Arbitrator. A dispute later arose regarding non-payment of the balance contract amount by SPPL, despite completion of supply and installation by Rim Limited. The matter was referred to arbitration. After considering the pleadings, documents and hearing both parties, the sole arbitrator concluded that SPPL was liable to pay the outstanding amount along with reasonable interest and costs of arbitration. Draft the operative portion of an Arbitral Award that the Arbitrator may issue in the above case in accordance with the provisions of the Arbitration and Conciliation Act, 1996.
Answer & Explanation:
IN THE MATTER OF ARBITRATION Between Rim Industries Limited - Claimant And Sanju Products Private Limited - Respondent ARBITRAL AWARD The dispute between the parties arose out of the contract dated ________ relating to supply and installation of machinery. The claimant contended that the respondent failed to pay the balance contract amount despite completion of contractual obligations. After examining the pleadings, documents and submissions of both parties, the undersigned arbitrator finds that the respondent is liable to pay the outstanding amount to the claimant. Award The Claimant, Rim Industries Limited, has successfully established that it duly performed its contractual obligations relating to the supply and installation of machinery under the Agreement entered into with the Respondent, Sanju Products Private Limited. The respondent Sanju Products Private Limited is hereby directed to pay to the claimant Rim Industries Limited the sum of ₹ ________ together with interest at __% per annum from the date of claim till realization. The respondent shall also bear the costs of arbitration amounting to ₹ ________. The Respondent shall pay the amounts awarded under Clauses 5 and 6 above within thirty (30) days from the date of receipt of this Award. All other claims, counterclaims, if any, and reliefs not expressly granted herein stand rejected. This Award is final and binding upon the parties in accordance with the provisions of the Arbitration and Conciliation Act, 1996. This award is made and signed on this ____ day of ________ at ________. (Signature of Arbitrator) Name: ____________ Sole Arbitrator
Topics: Arbitral Award
Related Questions in this Topic
- OG (Appellant) entered into a contract with GT Private Limited (Respondent). Disputes arose regarding payment of outstan...
- In a case, the learned Arbitrator reserved his Arbitral Award on 28th July 2012 but pronounced it only on 16th March 201...
- In a case, the learned Arbitrator reserved his Arbitral Award on 28th July 2012 but pronounced it only on 16th March 201...
- Creative Contractors Ltd (CCL), a listed Company entered into a long-term contract with Mahati Interiors (MI), an archit...
- Altas Limited ('Altas') entered into a contract with the Union of India after successfully bidding in a tender issued by...