Which of the following is an important ingredient of project appraisal under normal conditions ? (A) Accuracy of methods and measurements planned to be adopted is well adhered to (B) Objectivity of the proposal is highli
CS Executive · Financial and Strategic Management · PYQS · December 2022
Which of the following is an important ingredient of project appraisal under normal conditions ? (A) Accuracy of methods and measurements planned to be adopted is well adhered to (B) Objectivity of the proposal is highlighted so as to keep off from the bias and prejudices (C) Ensure the reliability of the data and projected statements (D) All of the above
Answer & Explanation:
Correct Answer: Option (D)
Official answer key: (D).
Topics: Financial Management
Related Questions in this Topic
- Assume that a firm has accurately calculated the net cash flows relating to an investment proposal. If the net present v...
- A firm has EBIT of ₹ 50,000. Market value of 10% debt is ₹ 80,000 and overall capitalization rate is 20%. Market value o...
- A firm has inventory turnover of 4 and cost of goods sold is ₹ 7,50,000. With better inventory management, the inventory...
- 80% of sales of ₹ 12,00,000 of a firm are on credit. It has a Receivable Turnover of 8. What is the Average collection p...
- A Company's Raw material storage period is 20 days; Finished goods storage period is 25 days; Receivables (Debtors) coll...