Saswat Dairy Ltd. (SDL) is planning to buy dairy plant costing ₹400 lakh. Milk Board provides 10% subsidy on the capital cost. It can process milk to produce cheese with the capacity of 1,800 tonnes per annum. The sellin

CS Professional · Financial, Treasury and Forex Management · PYQS · June 2015
Saswat Dairy Ltd. (SDL) is planning to buy dairy plant costing ₹400 lakh. Milk Board provides 10% subsidy on the capital cost. It can process milk to produce cheese with the capacity of 1,800 tonnes per annum. The selling price of cheese is taken as ₹50 per Kg. The management expects the life of the plant at 8 years and the depreciation shall be computed using straight line method. However, the plant can be sold at ₹50 lakh at the end of its useful life. The utilisation of plant is expected as below: Years 1 2 3 4 to 8 Capacity Utilisation 60% 70% 80% 90% The variable cost constituting primarily of the raw material (milk) is placed at 40% while the fixed expenses are ₹300 lakh per annum. The company pays tax @35%. The additional working capital required is ₹100 lakh. Find the following (b) NPV of the project

Answer & Explanation:

(b) Net Present value (NPV) of the project Year CFAT Scrap value Working Capital Total PV Factor @ 10%* Present value 1 24 24 0.9091 21.82 2 64.2625 64.2625 0.8264 53.11 3 99.3625 99.3625 0.7513 74.65 4 134.4625 134.4625 0.6830 91.84 5 134.4625 134.4625 0.6209 83.49 6 134.4625 134.4625 0.5645 75.90 7 134.4625 134.4625 0.5132 69.00 8 134.4625 50 100 284.4625 0.4665 132.70 PV of cash inflows 602.51 Less: Initial cash outflow (460.00) Net present value 142.51 lakh *Note: NPV is calculated on the basis of an assumption that cost of capital is 10%.

Topics: Capital Budgeting

Open in Interactive Practice Hub · Full Practice Hub · Chapter Weightage · More in this subject

Related Questions in this Topic