What are the documents to be verified by IS auditor in System Development Methodology? State briefly.

CS Professional · Information Technology and Systems Audit · PYQS · December 2021
What are the documents to be verified by IS auditor in System Development Methodology? State briefly.

Answer & Explanation:

The documents to be verified by IS auditor in System Development Methodology are enumerated below: Functional requirement Specifications; Software requirement Specification; Design Description; Software Code; Test Plan; Unit test results; Integration test results; Acceptance test results. Every time a change is made, a thorough testing should be done and documented.

Topics: Information Systems Audit