In a factory where piece work system is followed with guaranteed minimum wages of ₹120 for eight hours, incentive payments are made according to Rowan bonus scheme. The standard time per unit is 10 minutes. If in a five

CS Executive · Cost and Management Accounting · PYQS · December 2014
In a factory where piece work system is followed with guaranteed minimum wages of ₹120 for eight hours, incentive payments are made according to Rowan bonus scheme. The standard time per unit is 10 minutes. If in a five day week of 40 working hours the actual production is 300 units, what will be the total earnings of the worker —
(A) ₹640
(B) ₹720
(C) ₹750
(D) ₹800.

Answer & Explanation:

Correct Answer: Option (B)

Correct answer: (B) ₹720. Standard time for 300 units = 50 hours. Time saved = 10 hours. Rowan earnings = 40×15 + (10/50)×40×15 = 720.

Topics: Labour Costing