Section 28 of the Factories Act, 1948 provides that in a factory, every hoist and lift shall be properly maintained and thoroughly examined by a competent person at least once in every period of —

CS Executive · Industrial, Labour & General Laws · PYQS · June 2015
Section 28 of the Factories Act, 1948 provides that in a factory, every hoist and lift shall be properly maintained and thoroughly examined by a competent person at least once in every period of —
(A) Three months
(B) Six months
(C) Nine months
(D) Twelve months.

Answer & Explanation:

Correct Answer: Option (B)

Official answer key: (B).

Topics: Factories Act, 1948

Open in Interactive Practice Hub · Full Practice Hub · Chapter Weightage · More in this subject