Actual production during a month by worker-'X' is 1,000 units. If standard production per month per worker is 1,000 units and piece work rate is ₹5 per unit, the total monthly remuneration of worker 'X' under the Gantt's
CS Executive · Cost and Management Accounting · PYQS · June 2015
Actual production during a month by worker-'X' is 1,000 units. If standard production per month per worker is 1,000 units and piece work rate is ₹5 per unit, the total monthly remuneration of worker 'X' under the Gantt's Task and Bonus Scheme will be —
Answer & Explanation:
Correct Answer: Option (C)
Official answer key: (C).
Topics: Labour Costing
Related Questions in this Topic
- Which of the following is not an avoidable cause of labour turnover ?
- If standard time is 72 hours, then what would be time saved to getting same bonus under Halsey Plan and Rowan Plan ?
- Most of the firms prefer to treat the learners' wages as............as learners take more time than a trained worker.
- The following information is given to you: Standard output in 12 hours is 144 units. Actual output of a worker in 10 ...
- Priestman Production Bonus Plan is a :