Which of the following is not an objective of time-booking —

CS Executive · Cost and Management Accounting · PYQS · June 2015
Which of the following is not an objective of time-booking —
(A) Apportionment of overheads against jobs
(B) Preparation of payrolls
(C) Ascertaining idle time for the purpose of control
(D) Calculation of labour cost of jobs done.

Answer & Explanation:

Correct Answer: Option (B)

Official answer key: (B).

Topics: Labour Costing