Budgeted standard hours of a factory are 15,000. The capacity utilisation ratio for May, 2016 is 85% and efficiency ratio for the month is 120%. The standard hours for actual production in the month will be —

CS Executive · Cost and Management Accounting · PYQS · December 2016
Budgeted standard hours of a factory are 15,000. The capacity utilisation ratio for May, 2016 is 85% and efficiency ratio for the month is 120%. The standard hours for actual production in the month will be —
(A) 12,750
(B) 18,000
(C) 15,300
(D) 18,000

Answer & Explanation:

Correct Answer: Option (C)

Official answer key: (C).