Which of the following is not a part of job order cost sheet —

CS Executive · Cost and Management Accounting · PYQS · December 2016
Which of the following is not a part of job order cost sheet —
(A) Direct material
(B) Direct labour
(C) Actual factory overheads
(D) Applied factory overheads.

Answer & Explanation:

Correct Answer: Option (C)

Official answer key: (C).

Topics: Cost Accounting