Standard output per day per worker is 40 units. Incentive bonus for efficiency above 80% is ₹50 for every 1% increase up to 90% and above this ₹80 for every 1% increase. Kapil worked for 25 days and produced 910 units. T
CS Executive · Cost and Management Accounting · PYQS · December 2016
Standard output per day per worker is 40 units. Incentive bonus for efficiency above 80% is ₹50 for every 1% increase up to 90% and above this ₹80 for every 1% increase. Kapil worked for 25 days and produced 910 units. The amount of incentive paid to him will be —
Answer & Explanation:
Correct Answer: Option (A)
Official answer key: (A).
Topics: Cost Accounting
Related Questions in this Topic
- Which of the following is not included in cost accounts ?
- Besides the management, __________ and __________ are also benefitted in many ways by installing a good cost accounting ...
- Which of the following items is not included in Cost Accounts ?
- Cost Accounting is mostly __________ in its approach.
- Statement I: Although the Law of supply and demand to a great extent determine the price of an article, cost to the prod...