In a factory, the standard output in 8 hours is 220 units. A worker actually produces 242 units in the standard time. Wage rate is ₹8 per hour. The total wages paid to the worker under Emerson's plan will be —

CS Executive · Cost and Management Accounting · PYQS · December 2016
In a factory, the standard output in 8 hours is 220 units. A worker actually produces 242 units in the standard time. Wage rate is ₹8 per hour. The total wages paid to the worker under Emerson's plan will be —
(A) ₹83.20
(B) ₹76.80
(C) ₹193.60
(D) ₹99.20

Answer & Explanation:

Correct Answer: Option (A)

Official answer key: (A).