A written comprehensive order, with specification, material code and quantity sent to inform the purchase department, of a need for material is called —

CS Executive · Cost and Management Accounting · PYQS · December 2016
A written comprehensive order, with specification, material code and quantity sent to inform the purchase department, of a need for material is called —
(A) Purchase order
(B) Bill of material
(C) Purchase requisition
(D) Bin card.

Answer & Explanation:

Correct Answer: Option (B)

Official answer key: (B).

Topics: Cost Accounting