Following information is obtained from a standard cost card : Labour rate : 90 paise per hour Standard hours : 3 hours per unit Actual production data: Units produced : 250 Labour rate : ₹1.05 per hour Hours worked : 800 The labour cost variance will be —
(A) ₹175 (A)
(B) ₹165 (A)
(C) ₹190 (A)
(D) ₹165 (F).

Answer & Explanation:

Correct Answer: Option (B)

Official answer key: (B).

Topics: Cost Accounting