While preparing a flexible budget indirect wages was considered as a semi-variable expense. At 50% level of production it was estimated as ₹1,50,000. If it has a tendency to increase by 10% between 60% and 75% capacity a
CS Executive · Cost and Management Accounting · PYQS · December 2017
While preparing a flexible budget indirect wages was considered as a semi-variable expense. At 50% level of production it was estimated as ₹1,50,000. If it has a tendency to increase by 10% between 60% and 75% capacity and further will increase by another 5% when production crosses 75%, the amount of indirect wages at 90% level of production is: (A) ₹1,65,000 (B) ₹1,72,500 (C) ₹1,73,250 (D) None of the above
Answer & Explanation:
Correct Answer: Option (B)
Official answer key: (B).
Topics: Budgeting
Related Questions in this Topic
- Methods of cash budget are :
- A method of budgeting whereby all activities are re-evaluated each time a budget is set. Discrete levels of each activit...
- A factor which will limit the activities of an undertaking and which is taken into account in preparing budgets, is term...
- ............is prepared for the estimation of plant capacity to meet the budgeted production during the budgeted period.
- __________ is attainable under standard conditions.