During the third week of March, Mr. R. produced 420 units. The standard time allowed to produce one unit is 10 minutes. If he received wages for a guaranteed 48 hours per week at the rate of ₹5 per hour and bonus accordi
CS Executive · Cost and Management Accounting · PYQS · December 2017
During the third week of March, Mr. R. produced 420 units. The standard time allowed to produce one unit is 10 minutes. If he received wages for a guaranteed 48 hours per week at the rate of ₹5 per hour and bonus according to Hasley Plan, the total earning was: (A) ₹295 (B) ₹350 (C) ₹240 (D) ₹276.67
Answer & Explanation:
Correct Answer: Option (A)
Official answer key: (A).
Topics: Labour Costing
Related Questions in this Topic
- Which of the following is not an avoidable cause of labour turnover ?
- If standard time is 72 hours, then what would be time saved to getting same bonus under Halsey Plan and Rowan Plan ?
- Most of the firms prefer to treat the learners' wages as............as learners take more time than a trained worker.
- The following information is given to you: Standard output in 12 hours is 144 units. Actual output of a worker in 10 ...
- Priestman Production Bonus Plan is a :